Third main line on UP/Metra West Line started in September 2022 and is expected to be finished in July 2024.



Union Pacific Third Main Line Project | Geneva, IL - Official Website

Union Pacific is building a third railroad line on its UP/Metra West Line from Kress Road in West Chicago through all of Geneva. The 6-mile stretch of new rail will be set 20 feet south of the current tracks from Peck Road to Route 25. Heading east toward Kirk Road, the existing tracks will be shifted and the new line will be built on the north side.

73 Views
Unknown member
Oct 20, 2022

They can't run scoots now with 3 tracks